The Indoor Multifunction Stadium project is located in the Gelora Bung Karno area (GBK), Jakarta. This project is implemented with a design and built (lumpsump) system designed by the DIPA of the Jakarta Metropolitan Settlement Infrastructure Work Unit for the 2021-2023 fiscal year. The IMS project construction period was carried out for 540 days and its maintenance period for 180 days.

As the scheduler, Silvia is in charge of making the weekly progress report that consists of work progress in calculations and in the field to know the whole of working progress in real and future as the target, and making the breakdown of the work in Ms. Project.